Industrial Engineering at the Boeing Composite Wing Center

Executive Summary

As an Industrial Engineer on the Boeing 777X program, I was responsible for analyzing and scaling a highly complex manufacturing system composed of dozens of interdependent work cells, each constrained by physical resources such as machines, labor, tooling, and material flow.

My core focus was “rate readiness” - determining whether the system could meet future production targets, and if not, defining the optimal set of actions to close the gap. This required balancing tradeoffs between throughput improvements, capital investment, and operational risk under uncertainty.

I built data-driven models and decision frameworks to identify system bottlenecks, forecast future performance, and guide high-stakes decisions, including whether to invest millions in new equipment or instead rely on engineering and process improvements.

System Overview

Before diving into the analysis, it’s important to understand the physical system being optimized. So first, a quick summary of the engineering of an airplane wing:

The main load-bearing structure of an airplane wing (also known as the wing-box) is made of up several different components:

  1. The Upper and Lower “Skins.” Also known as Wing Panels. The upper panel is labeled 5 in the diagram below.

  2. The Front and Rear Spars. Labeled as 2 and 3. These are like the “spines” of the wing skeleton.

  3. The Stringers. Labeled as 7. These structures add rigidity to the wing panels (and allow for the movement of fuel between compartments in the wing).

  4. The Ribs. Labeled as 4. These plates line the interior of the wing-box, just like the ribs of a skeleton.

*Second image is the full scale 777X wing panel.

Illustration showing exploded view of airplane wing components, labeled with numbers indicating different parts, including structure and internal elements.
Large aircraft wing assembly in factory, blue lighting, workers in safety vests, industrial setting, National Geographic logo.

For the Boeing 777X, both pairs of panels and spars are over 100 ft long, and the ~90 stringers can range from 2 ft to 100 ft long. All of these components are fabricated at the Composite Wing Center in Everett, Washington. This was the building that I worked at as an Industrial Engineer from 2019 - 2022, focusing on system-level production performance.

Because some of the specific details are sensitive, proprietary information, I will have to be somewhat vague about the engineering process. But everything I’m going to share in this case study has been released by Boeing publicly.

Problem Framing: Scaling a Physical System

The core problem was straightforward in concept: Given a fixed set of physical resources and an increasing production target, how do we ensure the system can scale to meet demand?

This required continuously answering:

  • Where are the system’s true constraints?

  • What is the most effective way to remove or mitigate them over time?

These constraints were governed by physical realities: machine cycle times, labor availability, floor space, material constraints, and process variability. Even small inefficiencies or disruptions could propagate across the system and impact overall throughput.

Theory of Constraints

I will very briefly touch on a fundamental Industrial Engineering concept called the Theory of Constraints. It states that in order to improve the performance of a system, you must follow these steps:

  1. Identify the system's constraint(s)

  2. Decide how to exploit the system's constraint(s) 

  3. Subordinate everything else to exploit the constraint(s)

  4. Elevate the system's constraint(s)

  5. If in the previous steps a constraint has been broken, go back to step 1, but do not allow inertia to cause a system's constraint.

In practice, this became a continuous decision system. Constraints shifted over time due to changing demand, engineering improvements, and operational variability, requiring constant reassessment and reprioritization.

Manufacturing Process

Broadly speaking, the manufacturing process for all composite products follows the same general steps (including the components I described above):

  1. Raw carbon fiber material is formed into the shape of the part

  2. The part is cured in an autoclave (high pressure + temperature)

  3. Post-processing brings the part to final specification

This process is executed across many interconnected work cells, each responsible for a portion of the workflow. Below is a precedence diagram that visualizes the whole workflow of the manufacturing process.

Flowchart diagram with multiple paths labeled A. Spars, B. Panels, C. Stringers, D. Mixed. Contains nodes connected by arrows indicating process flow. Color-coded for sections: red (A), blue (B), green (C), yellow (D). Specific nodes and sequences are marked with "x4" and "x90" for repetition.

Even though the above diagram seems complex, this is only a tiny fraction of the complexity of the system.

Each work cell depends on a combination of:

  • Machinery and automation

  • Tooling and transport equipment

  • Skilled operators and inspectors

  • Raw and non-production materials

  • Time (ranging from hours to multiple shifts)

While this appears linear on paper, real production behavior was highly variable. Machine downtime, staffing gaps, quality issues, and upstream delays introduced non-deterministic behavior that had to be accounted for in all planning and forecasting.

Rate Readiness

My primary responsibility was driving rate readiness: ensuring that each part of the system could meet future production targets defined by the program’s rate ramp.

A rate ramp defines how many airplanes must be produced per month over time. Meeting this demand requires every work cell in the system to operate within strict time constraints.

These rates directly informed decisions around:

  • Capital investment

  • Engineering prioritization

  • Staffing and operational planning

If any work cell failed to meet required throughput, it risked becoming a bottleneck that constrained the entire system.

Bar graph showing monthly airplane production from Jan 2023 to Sep 2029, with increments at specific intervals.

Decision Framework: Increasing Throughput

When a work cell could not meet future rate requirements, there were two primary levers:

1. Improve Flow (Reduce Cycle Time)

  • Add staffing (when effective)

  • Optimize processes through engineering improvements

  • Introduce new methods or technologies

Tradeoffs:

  • Engineering effort and time

  • Implementation risk

  • Cost of experimentation

2. Increase Capacity

  • Add machines or equipment

  • Increase staffing to fully utilize existing equipment

Tradeoffs:

  • Multi-million dollar capital costs

  • Floor space limitations

  • Long lead times

  • Additional labor requirements

Choosing between these options required evaluating cost, risk, timing, and system-wide impact. These were rarely obvious decisions and often had long-term consequences.

Example: Capacity vs Throughput Tradeoff

In one of the most critical bottleneck work cells, there was strong pressure to purchase an additional machine: a multi-million dollar investment with significant space and staffing implications.

I led the analysis to determine whether this investment was necessary.

By combining:

  • Historical flow data

  • Time studies

  • Projected improvements from engineering initiatives

I built a forward-looking performance model under multiple scenarios.

The conclusion: With targeted process improvements, the system could meet future demand without additional capital investment.

This required aligning engineering and operations stakeholders and accepting some level of risk, but ultimately avoided unnecessary cost while maintaining rate readiness.

System-Level Bottleneck Analysis

Because no work cell operates in isolation, we extended this analysis across the entire system.

For each work cell, we compared:

  • Actual performance

  • Projected performance

  • Required performance based on rate

This allowed us to identify gaps between current capability and future requirements.

We then aggregated this into a system-level view, where:

  • Each column represented a work cell

  • Each value represented the performance gap

This made it possible to:

  • Identify the most critical bottlenecks

  • Prioritize interventions

  • Sequence improvements over time

Importantly, this was about identifying both the severity of the gap and timing. Some bottlenecks only became critical at higher production rates, so planning had to account for when constraints would emerge.

Data & Decision Infrastructure

To support this work, I developed analytical tools using SQL, Excel, and BI dashboards that transformed raw production data into actionable insights.

These tools enabled:

  • Real-time visibility into work cell performance

  • Projection of future throughput under different scenarios

  • Alignment across engineering and operations teams

This effectively created a decision-making layer that connected physical production behavior with planning and execution.

The below chart is an example of an analysis of an individual work cell where we can visualize actual and average current performance with projected rates into the future (if grey line is above red line, then there is a performance gap).

Flow chart comparing actual flow and rate requirements, showing blue bars for actual flow, a gray line for running average, a dashed gray line for flow projection, and a red line for rate requirement over various panels and rates.
Heatmap displaying different rates and values across various categories labeled A.1 to D.2, with colors indicating value intensity.

A consolidated version of this system analysis might look like this (columns are workcells, rows are production rates, and values are the severity of the performance gap):

Conclusion

The challenge was not optimizing individual processes, but orchestrating a complex, interdependent system under evolving constraints.

Every decision - staffing, tooling, process improvements, or capital investment - had cascading effects across the system. And the complexity magnifies when we take into account the resources of

  • headcount

  • tooling

  • raw material

As well as factors like

  • part quality

  • scrapped parts

  • inventory

  • logistical constraints and floorspace

  • raw material “expiration”

  • raw material supply chain considerations

  • and the interaction effects between all of these things.

This experience shaped how I approach complex systems today: Start from first principles, understand the real constraints, and design solutions that balance throughput, cost, and reliability at scale.